Step
1: Go through the materials available
on the website. Attempt to answer the on-line
scorecard |
 |
 |
 |
Step
2: If you feel you would like to go
through the eSCM assessment, obtain management
approval |
 |
 |
 |
Step
3: Confirm participation to Singapore Manufacturers' Federation (SMa Federation) and
nominate an internal coordinator |
 |
 |
 |
Step
4: Coordinator constitutes an internal
cross functional team and disseminates information
about the eSCM project |
|
|
 |
Step
5: Request for an audit through the
on-line requisition |
 |
 |
 |
Step
6: SMa Federation confirms the audit schedule |
 |
 |
 |
Step
7: Coordinator to lead the internal
assessment and collection of KPI data |
 |
 |
 |
Step
8: Auditor to carry out 2 day audit
and workshop |
 |
 |
 |
Step
9: Auditor to prepare report and submit |
 |
 |
 |
Step
10: Benchmarking |
|